Frame inspection in Manor Lakes

Bracing, tie-downs and the upper floor structure, while every connection can still be seen.

  • Walls, trusses and upper floor framed, roof cover on, no linings
  • 1 to 2 hours on site
  • Report within 24 hours
Price your inspectionLeave your details and a Manor Lakes inspector calls you back.

No obligation. We use your details for your quote and may contact you about it even if you don't finish.

Fully licensed & accredited

Stage3 of 7
When to bookWalls, trusses and upper floor framed, roof cover on, no linings
Time on site1 to 2 hours on site
Inspected againstAS 1684 (timber framing), AS 4100 or NASH for steel frames, the engineer's bracing and tie-down plan, NCC Part 3.4

What is included in a Manor Lakes frame inspection

  • Bracing sheets and straps intact and fixed
  • Strap ends bent over and nailed at the top chord
  • Tie-down straps and blocks complete
  • Strongback anchors on the upper floor
  • Shear blocks screwed to the engineer's detail
  • Upstairs walls bearing over floor trusses
  • Beam connections built as drawn
  • Top plates continuous or strapped at breaks
  • Truss positions within 1.5D of a stud
  • Joist hangers whole and fully fixed
  • Window and door openings within 25 mm
  • Damaged studs and plates replaced
  • Truss layout matching the approved plan
Why it matters here

Frame inspections on Manor Lakes builds

A double storey frame passes its loads down through connections that are hidden within weeks. On Manor Lakes frames in December 2025 and June 2026 we recorded strongbacks missing anchors, shear blocks without their screws, tie-down straps left half done and upstairs walls that did not sit over the trusses below. None of those can be seen once the plasterer arrives, which is why this stage carries more weight here than any other.

What we find at this stage in Manor Lakes

  • Strongbacks missing framing anchors
  • Shear block screws not installed
  • Strap brace ends loose at the top chord
  • Upstairs walls off the floor trusses
  • Tie-down straps and blocks incomplete
Tie-down straps and blocks left incomplete on a wall frame, found during a frame stage inspection in Manor Lakes
Tie-down straps and blocks left incomplete on a wall frame
Sample findings

Sample defects found during our frame inspections in Manor Lakes

Annotated findings from Frame inspections.

First floor shear blocks missing the screws the engineering calls for, found during a frame stage inspection in Manor Lakes
First floor shear blocks missing the screws the engineering calls for
Strap brace not bent over the end truss top chord and nailed off, found during a frame stage inspection in Manor Lakes
Strap brace not bent over the end truss top chord and nailed off
Bracing load transfer blocks not connected the way the engineering details them, found during a frame stage inspection in Manor Lakes
Bracing load transfer blocks not connected the way the engineering details them
Bracing sheet cracked and split, so it can no longer resist racking, found during a frame stage inspection in Manor Lakes
Bracing sheet cracked and split, so it can no longer resist racking

The other stages of a Manor Lakes build

  1. Bored piers inspection in Manor Lakes1Bored piersHoles drilled and cages placed, concrete not yet ordered
  2. Slab pre-pour inspection in Manor Lakes2Slab pre-pourSteel tied and formwork up, the day before the pour
  3. Lock-up (pre-plaster) inspection in Manor Lakes4Lock-up (pre-plaster)Roof, windows, cladding and external doors done, before plaster
  4. Fixing inspection in Manor Lakes5FixingDoors, architraves, skirtings and cabinets fitted, before painting
  5. Waterproofing inspection in Manor Lakes6WaterproofingMembrane cured in wet areas, no tiles laid
  6. Pre-handover (PCI) inspection in Manor Lakes7Pre-handover (PCI)Two to three weeks before the handover date

All construction stage inspections in Manor Lakes →

Guides

Construction stage guides for Manor Lakes

All guides →

Book a frame inspection in Manor Lakes

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Frame inspections in Manor Lakes: common questions

What is a strongback and why does it matter?

It is a member that stiffens a floor or ceiling and carries load to a support. If its anchors are missing it cannot do that job, and the result can be sagging or cracking upstairs later.

Is a double storey frame inspection longer?

Yes. Allow two to three hours, because the upper floor structure is checked as well as every wall.

Do you need the engineering?

Yes, please send the framing and bracing plans. Most of what we record on these frames is a difference between the detail and what was built.

What if the builder says the engineer will approve it?

That is a valid path. The report asks for written engineering approval, which keeps the record straight for the future.

Will the frame be looked at again later?

At lock-up we check that frame items have been fixed and that no bracing has been cut since.

What is not included?

Engineering certification, moisture content testing of timber, electrical and plumbing rough-in, and areas we cannot reach safely.